• Progress continues on the athletic stadium and elementary playground portion of the Capital Improvement Project. The initial field survey has been completed. Reference points and markers were staked out and will guide the construction of the new field, playground and structures. More than 4,300 yards of topsoil have also been striped and stockpiled for the project.

     

    The capital project also includes improvements to drainage in the playground and athletic stadium areas. An outlet drainage manhole has been tied into the system, a storm chamber system has been installed and manholes 1-4 have been installed and piped.