• As the end of the school year and summer vacation are getting closer, the Capital Improvement Project continues to move forward with further improvements to drainage in the areas of the athletic stadium and elementary playground.

     

    Last week, an additional 1,800 yards of topsoil were stripped and stockpiled, approximately 40,000 square feet of ball field were subgraded and 20 trees were planted behind the stadium and mulched.

     

    Additionally, three more drainage manholes were placed, approximately 1,200 feet of 10 inch drainage piping was installed, approximately 85 “Y” inlets for field drainage were installed and the layout of drainage and drywells continued.