• The capital project continues to move ahead this week with work being done on the athletic stadium, track, playground, elementary alarm system and high school gymnasium.

     

    This week, posts were installed for the track’s perimeter fencing and fine grade preparation was completed for track paving. Additionally, the water line to the bleachers was completed and all track trench and drain were closed and completed.

     

    Subgrade for the elementary playground was established and installation of the playground area drainage began. Placing and compacting of fill for the softball field also started this week.

     

    Wires for the new fire alarm system at N.A. Walbran Elementary continued to be run and work began on the creation of an ADA-compliant elementary bus loop.

     

    At the Jr./Sr. High School, sanding of the floor in the Davis Gymnasium continued.