• Some recent improvements have been made to ensure that N.A. Walbran Elementary is accessible to all of our students and guests. A new ADA ramp was installed at the elementary school’s main entrance and new sidewalks and curbs were formed and poured in the surrounding area. New sidewalks were also formed surrounding the playground area and underdrain at the playground was installed.

     

    At the site of the athletic complex, scoreboard footers were completed, the flagpole foundation was installed and the track pavement was treated with a binder coat to prepare for the installation of the rubberized track surface. Additionally, tree removal and extra grading were completed, installation of 10-inch drainage continued, and fill and compaction of soil at the softball field were done.

     

    Wire continued to be run inside the elementary school for the new fire alarm system, and at the Jr./Sr. High School, sanding of the floor in the Davis Gymnasium continued.