• The Capital Project continues to move full steam ahead. Recent work/progress includes:

     

    Elementary School School Building

    • Started installation of new fire panel; continuing to run wires
    • Completed concrete in bus loop
    • Started installation of bottle fillers

     

    Track

    • Completed paving
    • Installed footers for discus and shot put areas
    • Continuing to work on fencing around track

     

    Softball/Kickball Fields

    • Installed posts for backstops and foul lines
    • Installed piping and gravel blanket at softball field
    • Installed 360’ of 10” SMT piping
    • Installed two more dry wells

     

    Playground

    • Prepared walking path around play area

     

    Junior-Senior High School Building

    • Completed sanding of gym floor
    • Sealed gym floor
    • Installed new tile between bathroom doors and music room across from gym
    • Installed new bottle fillers near music room