Capital Project Update - August 3, 2018
-
Elementary School Building
- Worked on North /South Sidewalk extension
- Continued running wires for new alarm system
- Installed water fountains with bottle fillers in hallways
Track
- Installed approximately 40 trees
- Installed stone dust and border at shot put
Softball/Kickball Fields
- Worked on softball and kickball backstop installation
- Completed final grading for gravel blanket at softball field
Playground
- Started installation of new playground equipment
Junior-Senior High School Building
- Applied another coat of sealer on gym floor
- Began painting lines on gym floor
- Installed two additional bottle filling stations in gym hallway