• Parts of our buildings and grounds looked very different when students, teachers and staff returned for the 2018-2019 school year, last week. Our continuing Capital Improvement Project has provided visible improvements to the elementary playground, adjacent athletic complex and high school gymnasium. Recent work/progress includes:

    • Elementary playground was completed, including wood fiber and safety inspection
    • Installed fence guard around track
    • Installed 800’ of 10” drainage, 500’ of 6" drainage and four drywells
    • Finished softball field area, including completion of guard rail
    • Finished scoreboard installation
    • Additional general grading and placement of topsoil