• Work on our Capital Improvement Project is wrapping up. While the renovated fields will not be available for use until next fall, to allow time for the sod and surrounding grass to fully take hold, much of the major construction and renovation work has been completed. Some of the most recent progress includes:

    • Placed and graded more than 2,000 yards of topsoil
    • Installed approximately 900’ of stone to surface on drainage trenches
    • Installed clay at bases at kickball field
    • Completed enclosure under bleachers
    • Poured footers for new basketball hoops
    • Removed construction equipment and fencing
    • Continued hydro seeding